Abu Dhabi Airport District Cooling Plant, Energy Transfer Stations And Chilled Water Distribution Network

Abu Dhabi, UAE

General Information

Client: Abu Dhabi Airports Company (ADAC)
Abu Dhabi International Airport is the second largest international airport in UAE. It has three operational passenger terminals and is spread over an area of 3,400 hectares (8,500 acres).
Location: Abu Dhabi, UAE
Completion Date: January 2016
Consultant: KBR
Contract Type: Design, Supply, Installation Supervision, and Commissioning of the Integrated Instrumentation, PLC, and SCADA System
Cooling Capacity: 55,000 RT
TES Tank: 2x 25,000 Ton-Hr Thermal Energy Storage (TES) tank

Project Scope:

This is one of the country’s biggest districts cooling plant serving Abu Dhabi’s new Midfield Terminal Building (MTB). With a capacity of 55,000 tones of refrigeration, the district cooling plant provides air conditioning for the MTB through 18 chillers and two thermal energy storage tanks.

The district cooling system meets rigorous international green building standards (Estidama) and utilizes innovative technology to increase energy efficiency and provide sustainable air conditioning for the MTB.

Process:

District Cooling provides chilled water from a centralized cooling station, through a network of pipes, for air-conditioning purposes.

Our Solution:

Redundant Allen-Bradley ControlLogix PLC System; Redundant Server-Client Rockwell Automation FactoryTalk View Site Edition SCADA System, and Siemens/E+H Instrumentation system.