Vista Automation has successfully completed Factory Acceptance Test for the Metering Skid Control Panel for Gas Pipeline Project in Nigeria.

Vista Automation’s scope of work for this project includes the design, supply, manufacturing, programming, testing, and commissioning of the PLC, Flow Computer and Supervisory System. The project includes a total of five Custody Transfer Metering Station which consists of 24 streams. Each station package consists of 3-duty orifice-Stream, one standby Ultrasonic Stream, and one Ultrasonic Check Meter Stream.

A total of 24 FloBoss S600+ flow computers were supplied for this project along with three redundant Siemens S7-1500 PLC system, and three Independent WinCC Supervisory SCADA system.